Piping Febrication

Steel Fabrication :

Fabrication which is a WBS element is known as the higher level of pipe rack fabrication as well as the equipment access platform fabrication. While the progress trackking sheet includes The general arrangement drawing list, project area name, work pack number, fabrication start and finish date another additional spread sheet or system should be there to include the fabrication status of each assembly member for each GA drawing. This sheet or system is known as steel tracker sheet/system.

The progress tracking sheet nedds to be linked with the steel tracker sheet to update the fabrication status of each GA drawing.

The following structure can draw a picture of the hierarchy of the structure which represents how steel fabrication progress is tracked and monitored---